Franklin

Date: 
October 2019 to September 2020

Man Hours: 700+
System Hours: 2600

Technicians: Habitat Supervisor and Habitat Technician

Scope:  The aim was to provide a monitored and controlled environment for their engineers on board to carry out fibre-splicing on the well head.  

StS provided Baker Hughes with two Habitats over an 11 month period for this project. All hot works had to be completed while the platform was in full production due to the cost involved. The scope was completed without delay which allowed for normal operations to proceed as planned. 

Result: StS personnel worked closely alongside Fairfield Energy engineers to ensure everything worked safely according to plan without any incidents or delays.

Location: 
Franklin Field, North Sea